Status of Project

Status of The Project

Last Year Update

Bhaisakh – Chaitra 2080

A. Preliminary/Preparatory Works:
1. Application for purchasing Explosives forwarded from Department of Electricity
Development to Ministry of Energy, Ministry of Home Affairs, Ministry of Defense,
Nepal Army and Indian Embassy.

B. Civil Works
1. Slope Protection work at powerhouse area is completed upto EL 687.00 m
2. Excavation of Powerhouse foundation is completed upto EL 685.00 m
3. Base Preparation of Headpond foundation.

4. Excavation and preparation for Vertical Shaft Portal is ongoing.

C. Hydro Mechanical Works
1. Discussion and Negotiation with potential bidder for Hydromechanical Works.
2. Design of Gates, trashrack, bellmouth, pipe bends, bifurcation and optimization of
penstock pipe is ongoing.

D. Electromechanical Works
1. Discussion and Negotiation with potential bidder for Electromechanical Works.

E. Transmission Line Works

1. Application submission to Nepal Electricity Authority for voltage level change from
220 kV to 132 kV for Transmission Line.
2. Discussion and Negotiation with potential bidder for Transmission Line Works.

Initial Phase. 

  • DOED Survey License
  • Environmental Impact Assessment Study Approved By Ministry of Energy
  • Generation License
  • Transmission Line Survey License Applied to DOED
  • BANK FINANCIAL CLOSURE with SIDDHARTHA BANK LIMITED (SINGLE BANK)
  • POWER PURCHASE AGREEMENT with Nepal Electricity Authority
  • Due Deligence Audit
  • The Survey, Detailed Design, Technical, and DPR with Hydro Consult Engineering Limited
  • Construction of Camp Facilities Completed
  • Civil Construction Contractor Mobilized at Site
  • Powerhouse Excavation Work in Progress

 

Isuwa Energy Under Construction